Brickwork Project Details
Canary Wharf Data Centre, London
|
Client: Wood Wharf General/Cable and Wireless
Package Value: 20k
Brickwork Project Overview
- Design and Construction of new Data Centre.
- A brownfield development on the site of an old mill, tannery and former sewage treatment works.
Package Details
- Procurement and installation of all blockwork and accessories
- Provision of scaffolding and safety scaffolding
- A small package with logistical headaches and a very tight construction programme
- Congested site located 20m above Jubilee line